Help me understand this report

  • May 29, 2024
  • 3 replies
  • 299 views

Elan
Forum|alt.badge.img

I understand that the “Add your Team” customer task has been completed 15 times.

It also looks like it has been late 7% of the time… We’ve allotted 3 business days to get it done…

Where I’m scratching my head is- What does the -15 days mean? 

 

Best answer by harrisclarke

Hi @Elan -- the “-15” means this task is completed on average 15 days prior to its due date (which tells me it is likely often completed prior to it being assigned). 

The “Average Completed Duration” is an average of how many days before or after task assignment was the task marked “Done”

3 replies

Elan
Forum|alt.badge.img
  • Author
  • Inspiring
  • May 29, 2024

Same with this: 

@chrishaleua @harrisclarke any insights? I’m not the data guy I used to be haha


harrisclarke
Forum|alt.badge.img
  • Community Manager
  • Answer
  • May 29, 2024

Hi @Elan -- the “-15” means this task is completed on average 15 days prior to its due date (which tells me it is likely often completed prior to it being assigned). 

The “Average Completed Duration” is an average of how many days before or after task assignment was the task marked “Done”


Elan
Forum|alt.badge.img
  • Author
  • Inspiring
  • May 29, 2024

Ahhh just as I suspected - I’ll have to dig into that. Thank you so much!